Reading insulation specs: 22 07 00 and 23 07 00
On a project manual organized by CSI MasterFormat, plumbing insulation is usually Section 22 07 00 and HVAC insulation 23 07 00, sometimes split into separate sections for duct, equipment and piping. These sections decide what you price. Read them first, and when they disagree with the drawings, the spec normally governs.
The three parts
- Part 1, General: submittals, quality standards, and sometimes scope notes such as "existing piping is not to be insulated".
- Part 2, Products: the materials allowed, usually by ASTM standard: mineral fiber pipe insulation (ASTM C547), flexible elastomeric (ASTM C534), cellular glass (ASTM C552), and the jackets and vapor retarders (for example ASTM C1136 facings). This tells you which products you can price.
- Part 3, Execution: installation requirements and, most important for a takeoff, the insulation schedules.
The schedules are the takeoff's rules
Part 3 usually ends with tables by system and location: domestic cold water, hot water and return, storm, heating hot water, chilled water, condensate, refrigerant suction and liquid, and duct by type (supply, return, outside air, exhaust). For each one they give:
- the material;
- the thickness, often stepping up with pipe size (for example, one thickness through 1-1/4 inch and a thicker one from 1-1/2 inch);
- where it applies: indoors concealed, indoors exposed, outdoors, in mechanical rooms;
- the field-applied jacket, if any.
Some specs schedule pipe by fluid temperature instead of system name. Map each system to its operating temperature range, then read the thickness.
Exceptions and exclusions
Look for the list of items not to be insulated: unions, flexible connectors, nameplates, vent piping, sanitary piping that isn't heat-traced, underground piping (or piping only where the spec calls for it), and factory-insulated equipment. Each one you miss either inflates the bid or leaves a hole in it.
Energy code minimums
Many specs require thicknesses no less than ASHRAE 90.1 or the IECC requires for the fluid temperature and pipe size. If the spec cites a code table without listing thicknesses, look up the edition the project is under; don't assume.
When the spec and drawings disagree
A drawing note or schedule may call for something different from the spec. The contract documents' order of precedence decides, and the spec usually wins on materials and thicknesses. Note the conflict in your bid or send an RFI.