How to do a mechanical insulation takeoff

An insulation takeoff turns a mechanical and plumbing bid set into quantities you can price: linear feet of pipe insulation by service, size and thickness, fitting and valve counts, square feet of duct insulation, and the jacketing and accessories that go with them. This is the order that keeps it accurate and checkable.

1. Read the scope before you measure

Start with the specification, not the drawings. The insulation sections (usually 22 07 00 for plumbing and 23 07 00 for HVAC) tell you which systems get insulated, with what material, at what thickness by pipe size, and with which jacket indoors, outdoors, concealed and exposed. Make a short scope table before you open a plan:

SystemMaterialThickness by sizeJacket
Domestic cold waterFiberglass1/2" through 1-1/4": 1/2"; 1-1/2" and up: 1"ASJ; PVC where exposed
Domestic hot water and returnFiberglassto 1-1/4": 1"; 1-1/2" and up: 1-1/2"ASJ; PVC where exposed
Supply duct, concealedDuct wrap1-1/2", 3/4 lbFSK

Values above are an example layout only. Use the thicknesses your specification lists; many specs follow the minimums in ASHRAE 90.1 or the IECC and some exceed them.

Note what the spec leaves out as carefully as what it includes: systems not listed (vent, often sanitary unless heat-traced), existing piping, and items "not to be insulated" such as unions or flexible connectors.

2. List the sheets that carry your work

Go through the set once and mark the plumbing plans, the HVAC piping and ductwork plans, enlarged plans, riser diagrams, isometrics, schedules and details. Watch for:

3. Measure pipe by service, size and thickness

Trace each run on the plans and record its length against its service (cold water, hot water, hot water return, storm, heating water, chilled water, condensate, refrigerant) and its size. Sizes come from the drawing callouts; where a run isn't labeled, follow it back to the last labeled size, or to the riser diagram or fixture schedule. Keep runs separate where the thickness changes with size.

4. Count fittings and valves

Count 90s, 45s and tees on each insulated run by service and size. Each takes a preformed fitting cover sized by pipe and insulation wall; see the fitting cover size chart. Count valves, strainers and other specialties separately: the spec says whether they're insulated, and many are priced as labor or as removable covers rather than as pipe.

5. Duct: square feet, not linear feet

Duct insulation is priced by area. For each duct size, multiply the outside perimeter by the length: 2 × (width + height) ÷ 12 for rectangular duct, π × diameter ÷ 12 for round. Board adds four times its thickness to the perimeter. Then add the full rolls or boxes, foil tape and pins. The duct wrap and board calculator does this for one run.

6. Jacketing and accessories

7. Price and check

Apply your material prices, labor rates and waste, then check the takeoff against the drawings: does every riser appear on every floor it passes? Does each fixture have its drops? Do the totals by service look right for the size of the building? A takeoff you can trace line by line back to the sheet is one you can defend when the bid is questioned.