How to do a mechanical insulation takeoff
An insulation takeoff turns a mechanical and plumbing bid set into quantities you can price: linear feet of pipe insulation by service, size and thickness, fitting and valve counts, square feet of duct insulation, and the jacketing and accessories that go with them. This is the order that keeps it accurate and checkable.
1. Read the scope before you measure
Start with the specification, not the drawings. The insulation sections (usually 22 07 00 for plumbing and 23 07 00 for HVAC) tell you which systems get insulated, with what material, at what thickness by pipe size, and with which jacket indoors, outdoors, concealed and exposed. Make a short scope table before you open a plan:
| System | Material | Thickness by size | Jacket |
|---|---|---|---|
| Domestic cold water | Fiberglass | 1/2" through 1-1/4": 1/2"; 1-1/2" and up: 1" | ASJ; PVC where exposed |
| Domestic hot water and return | Fiberglass | to 1-1/4": 1"; 1-1/2" and up: 1-1/2" | ASJ; PVC where exposed |
| Supply duct, concealed | Duct wrap | 1-1/2", 3/4 lb | FSK |
Values above are an example layout only. Use the thicknesses your specification lists; many specs follow the minimums in ASHRAE 90.1 or the IECC and some exceed them.
Note what the spec leaves out as carefully as what it includes: systems not listed (vent, often sanitary unless heat-traced), existing piping, and items "not to be insulated" such as unions or flexible connectors.
2. List the sheets that carry your work
Go through the set once and mark the plumbing plans, the HVAC piping and ductwork plans, enlarged plans, riser diagrams, isometrics, schedules and details. Watch for:
- Overall plans broken into area plans: measure the area plans, not both.
- Demolition plans: existing and removed work isn't in your scope.
- The scale: check every sheet's printed scale, and check it against a known dimension. A reduced print (a large sheet printed on a small page) makes every length short.
3. Measure pipe by service, size and thickness
Trace each run on the plans and record its length against its service (cold water, hot water, hot water return, storm, heating water, chilled water, condensate, refrigerant) and its size. Sizes come from the drawing callouts; where a run isn't labeled, follow it back to the last labeled size, or to the riser diagram or fixture schedule. Keep runs separate where the thickness changes with size.
- Verticals: risers between floors come from the riser diagram and floor-to-floor heights; storm leaders run from the roof drain down to where they leave the building.
- Drops to fixtures and equipment: plans show where a line drops but not how far. Most estimators carry an allowance per drop (8 feet is common) unless an elevation or detail gives the length.
- Notes that state lengths ("run 40 ft to the existing main") count, even where the drawing is shorter.
4. Count fittings and valves
Count 90s, 45s and tees on each insulated run by service and size. Each takes a preformed fitting cover sized by pipe and insulation wall; see the fitting cover size chart. Count valves, strainers and other specialties separately: the spec says whether they're insulated, and many are priced as labor or as removable covers rather than as pipe.
5. Duct: square feet, not linear feet
Duct insulation is priced by area. For each duct size, multiply the outside perimeter by the length: 2 × (width + height) ÷ 12 for rectangular duct, π × diameter ÷ 12 for round. Board adds four times its thickness to the perimeter. Then add the full rolls or boxes, foil tape and pins. The duct wrap and board calculator does this for one run.
6. Jacketing and accessories
- Field-applied jacket (PVC or aluminum) by the square foot of insulation surface: π × insulated OD ÷ 12 per foot. See the jacket calculator.
- Large pipe past the largest tubular elastomeric size is wrapped from sheet; see the sheet rubber calculator.
- Tacks for fitting covers, tape, adhesive and mastic, at your own rates.
7. Price and check
Apply your material prices, labor rates and waste, then check the takeoff against the drawings: does every riser appear on every floor it passes? Does each fixture have its drops? Do the totals by service look right for the size of the building? A takeoff you can trace line by line back to the sheet is one you can defend when the bid is questioned.