How to price duct insulation per square foot

Duct insulation is bid by the square foot, but a single all-in square-foot number hides most of what moves the price. Build it from the takeoff instead: square feet by insulation type, then material, accessories, labor and markup, each on its own line.

1. Square feet by type and location

Start from the duct takeoff, split the way the specification splits it: supply, return, outside air and exhaust, and indoor concealed, indoor exposed and outdoor. Each split can take a different product.

The wrap versus board guide covers the square-foot difference in detail.

2. Material per square foot

Price each product per square foot from your supplier's quote. Wrap is sold by the roll and board by the box, so divide the price by the square feet in the roll or box. Add your waste allowance as a percentage of square feet. Then round up to whole rolls or boxes for the order, not for the bid.

3. Accessories

4. Labor

Labor is square feet ÷ your crew's production rate per day × your daily labor cost. Use separate rates for wrap, board and outdoor jacketing, since each installs at a different speed. Adjust the rate for height, access and congested ceilings rather than padding the material.

5. Markup and the bid

Total material, accessories and labor, then apply overhead and profit. Report a square-foot figure for each type so the general contractor can compare it, but keep the build-up underneath. When a quantity or a supplier price changes, you only re-price the line it touches.

InsulEngine does this build-up on your own cost book, from duct it measures on the plans. You can see how the duct takeoff works.

Questions

Should I use one blended price per square foot?

Only as a check. Wrap, board and outdoor jacketed board differ a lot in material and labor, so a blend is wrong whenever a job's mix differs from the average.

Where does waste go, square feet or price?

Add it to the square feet you buy and install, so material and labor both carry it.

How are pins counted?

Divide each face's area by the spacing your specification or NAIMA guidance gives, for each type and location. Board takes pins on every face.